Location: Singapore

Client: AMNGR

Project year: 2013

Project type: Equipment overhauling

GOE Role: Project Manager

Workscope:

  • Removing filter-silencer
  • Removing air suction,
  • Air diffuser removing
  • Removing impeller, 
  • Removing hex collar screw at the impeller hub,
  • Filled tapped hole with grease and screw in extracting device,
  • Impeller pulled out and removed,
  • Removed diffuser and shaft,
  • Removed gas outlet flange from turbine end,
  • Pulling out nozzle ring, inspected for cracks at the guide vanes,
  • Removed complete bearing housing,
  • Dismantled radial bearing with thrust ring and thrust bearing,
  • check for wear,
  • Cleaning all parts,
  • Replaced bearing,
  • Replaced thrust ring,
  • Replaced ring piston,
  • Replaced O rings